Ref: PMBOK® guide 5th ed. Page 10.
2 C
Ref: PMBOK® guide 5th ed. Page 10.
3 D
Ref: PMBOK® guide 5th ed. Page 11.
4 D
Ref: PMBOK® guide 5th ed. Page 13.
5 C
Ref: PMBOK® guide 5th ed. Page 15.
6- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 15.
7- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 15.
8- 2(A, B)
Ref: PMBOK® guide 5th ed. Page 15.
9 A
Ref: PMBOK® guide 5th ed. Page 15.
10- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 20.
11- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 23.
12 A
Explanation: EAC=BAC/CPI
CPI=EV/AC=$20,000/$25,000=0.8
EAC=23,000/0.8=28,750
Estimate at completion=$28,750.
13 B
Ref: PMBOK® guide 5th ed. Page 25.
14- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 28.
15 D
Explanation: VAC=BAC-EAC
=10,000-15,000
VAC=-$5,000
16- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 34.
17- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 36.
18 D
Ref: PMBOK® guide 5th ed. Page 37.
19- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 58.
20 A
Ref: PMBOK® guide 5th ed. Page 224.
21 A
Ref: PMBOK® guide 5th ed. Page 224.
22 D
Ref: PMBOK® guide 5th ed. Page 224.
23 D
Ref: PMBOK® guide 5th ed. Page 224.
24 C
Ref: PMBOK® guide 5th ed. Page 224.
25 B
Ref: PMBOK® guide 5th ed. Page 224.
26 A
Ref: PMBOK® guide 5th ed. Page 224.
27 D
Ref: PMBOK® guide 5th ed. Page 224.
28 D
Ref: PMBOK® guide 5th ed. Page 224.
29 D
Ref: PMBOK® guide 5th ed. Page 224.
30 D
Ref: PMBOK® guide 5th ed. Page 224.
31 D
Ref: PMBOK® guide 5th ed. Page 224.
32 C
Ref: PMBOK® guide 5th ed. Page 224.
33 C
Ref: PMBOK® guide 5th ed. Page 224.
CV = EV – AC=105,000-100,000=$5,000
34 C
Ref: PMBOK® guide 5th ed. Page 224.
SV = EV – PV=$105,000-$100,000=$5,000
35 A
Ref: PMBOK® guide 5th ed. Page 224.
VAC = BAC – EAC=100,000-105,000=-$5,000
36 B
Ref: PMBOK® guide 5th ed. Page 224.
CPI = EV/AC=105,000/100,000=1.05
37 C
Ref: PMBOK® guide 5th ed. Page 224.
SPI = EV/PV=$105,000/$90,000=1.166
38 C
Ref: PMBOK® guide 5th ed. Page 224.
EAC = BAC/CPI=$100,000/1.16=$86,206.89
39 C
Ref: PMBOK® guide 5th ed. Page 224.
EAC = AC + BAC – EV=$105K+$100K-$100K=$105K
40 C
Ref: PMBOK® guide 5th ed. Page 224.
41 C
Ref: PMBOK® guide 5th ed. Page 224.
EAC = AC + [(BAC – EV)/(CPI x SPI)]
EAC=$105K+[($100K-$110K)/(1.1*0.95)]
EAC=$95,430.6
42 B
Ref: PMBOK® guide 5th ed. Page 224.
ETC = EAC – AC=$100K-$105K=-$5K
43 A
Ref: PMBOK® guide 5th ed. Page 224.
44 B
Ref: PMBOK® guide 5th ed. Page 224.
45 A
Ref: PMBOK® guide 5th ed. Page 224.
46 B
Ref: PMBOK® guide 5th ed. Page 224.
47 B
Ref: PMBOK® guide 5th ed. Page 224.
48 B
Ref: PMBOK® guide 5th ed. Page 224.
49 D
Ref: PMBOK® guide 5th ed. Page 224.
50 D
Ref: PMBOK® guide 5th ed. Page 224.
51 B
Ref: PMBOK® guide 5th ed. Page 224.
52 A
Ref: PMBOK® guide 5th ed. Page 224.
53 B
Ref: PMBOK® guide 5th ed. Page 224.
54 A
Ref: PMBOK® guide 5th ed. Page 224.
55 B
Ref: PMBOK® guide 5th ed. Page 224.
56 B
Ref: PMBOK® guide 5th ed. Page 224.
57 A
Ref: PMBOK® guide 5th ed. Page 224.
58 A
Ref: PMBOK® guide 5th ed. Page 224.
59 C
Ref: PMBOK® guide 5th ed. Page 224.
60 B
Ref: PMBOK® guide 5th ed. Page 224.
61 D
Ref: PMBOK® guide 5th ed. Page 224.
62 A
Ref: PMBOK® guide 5th ed. Page 224.
CV=EV-AC
CV=20,000-25,000=-$5,000
63 C
Ref: PMBOK® guide 5th ed. Page 224.
SV=EV-PV
CV=20,000-22,000=-$2,000
64 B
Ref: PMBOK® guide 5th ed. Page 224.
VAC=BAC-EAC
VAC=25,000-20,000=$5,000
65 A
Ref: PMBOK® guide 5th ed. Page 224.
CPI=EV/AC
=20,000/25,000=0.8
66 C
Ref: PMBOK® guide 5th ed. Page 224.
SPI=EV/PV
=20,000/22,000=0.91
67- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 23.
68 C
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: EAC=AC+BAC-EV
=25,000+23,000-20,000
Estimate at completion=$28,000.
69 C
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: EAC = AC + [(BAC – EV)/(CPI x SPI)]
EAC=25,000 + [(23,000-20,000)/(CPI*SPI)]
CPI=EV/AC=20,000/25,000=0.8
SPI=EV/PV=20,000/22,000=0.91
EAC=25,000+[3,000/(0.8*0.91)]
Estimate at completion=$29,120.88 which is $29,121 when rounded off.
70 C
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: ETC=EAC-AC
=27,000-25,000
ETC=$2,000
71 C
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: TCPI = (BAC – EV)/(BAC – AC)
=(25,000-23,000)/(25,000-24,000)
TCPI=2
72 A
Ref: PMBOK® guide 5th ed. Page 224.
TCPI = (BAC – EV)/(EAC – AC)
=(25,000-23,000)/(26,000-24,000)
=2,000/2,000
TCPI=1
73 A
Ref: PMBOK® guide 5th ed. Pg 128.
74 A
Ref: PMBOK® guide 5th ed. Page 111.
75 C
Ref: PMBOK® guide 5th ed. Page 72.
76 A
77 D
Ref: PMBOK® guide 5th ed. Page 292.
Explanation:
The total number of communication channels = n(n – 1)/2, where is the number of stakeholders.
n= 5 onsite members + 3 offshore members + 1 onsite stakeholder + 1 offshore stakeholder + 1 PM=11
# of communication channels=11*10/2=55.
78 B
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: For future work that will be accomplished at the planned rate:
AC=$10,000
EV=$6,000
BAC=$12,000
EAC=AC+BAC-EV=10000+12000-6000
EAC=$16000
79 A
Ref: PMBOK® guide 5th ed. Page 224.
Explanation: For work that is proceeding per plan, the cost of completing the remaining authorized work is
ETC=EAC-AC
=20,000-13,000
ETC=$7,000
80 A, B, C, D
Ref: PMBOK® guide 5th ed. Page 29.
No comments:
Post a Comment