A. $9,569.37
B. $100,000
C. $95,430.6
D. $114,569.37
42) The estimate at completion for your project is $100,000 and the actual cost is $105,000. What is the Estimate to complete assuming that work is proceeding on plan?
A. $105,000
B. -$5,000
C. $5,430.6
D. $5000
43) The efficiency that must be maintained in order to complete the current EAC is:
A. (BAC – EV)/(EAC – AC)
B. (BAC – EV)/(BAC – AC)
C. BAC/CPI
D. EAC – AC
44) The efficiency that must be maintained in order to complete on plan is:
A. (BAC – EV)/(EAC – AC)
B. (BAC – EV)/(BAC – AC)
C. BAC/CPI
D. EAC – AC
45) If TCPI (To Complete Performance Index) is greater than 1, the project is:
A. Harder to complete
B. Easier to complete
C. Cannot be determined
D. Neither hard nor easy to complete
46) If TCPI (To Complete Performance Index) is lesser than 1, the project is:
A. Harder to complete
B. Easier to complete
C. Cannot be determined
D. Neither hard nor easy to complete
47) You are reporting that your project has an SPI greater than 1 and CPI is greater than 1. This means your project is:
A. Ahead of schedule and over planned cost
B. Ahead of schedule and under planned cost
C. Behind schedule and over planned cost
D. Behind schedule and under planned cost
48) You are reporting that your project has an SPI equal to 1 and CPI equal to 1. This means your project is:
A. Ahead of schedule and over planned cost
B. On schedule and on planned cost
C. On schedule and over planned cost
D. Behind schedule and on planned cost
49) You are reporting that your project has an SPI lesser than 1 and CPI lesser than 1. This means your project is:
A. Ahead of schedule and under planned cost
B. Ahead of schedule and over planned cost
C. Behind schedule and under planned cost
D. Behind schedule and over planned cost
50) You are reporting that your project has an SPI lesser than 1 and CPI greater than 1. This means your project is:
A. Ahead of schedule and under planned cost
B. Ahead of schedule and over planned cost
C. Behind schedule and over planned cost
D. Behind schedule and under planned cost
51) You are reporting that your project has an CPI lesser than 1 and SPI greater than 1. This means your project is:
A. Ahead of schedule and under planned cost
B. Ahead of schedule and over planned cost
C. Behind schedule and under planned cost
D. Behind schedule and over planned cost
52) You are reporting that your project has a positive Variance at completion. This means your project is:
A. Under planned cost
B. Over planned cost
C. On planned cost
D. Cannot be determined
53) You are reporting that your project has a negative Variance at completion. This means your project is:
A. Under planned cost
B. Over planned cost
C. On planned cost
D. Cannot be determined
54) You are reporting that your project has a positive cost variance. This means your project is:
A. Under planned cost
B. Over planned cost
C. On planned cost
D. Cannot be determined
55) You are reporting that your project has a negative cost variance. This means your project is:
A. Under planned cost
B. Over planned cost
C. On planned cost
D. Cannot be determined
56) You are reporting that your project has a positive schedule variance. This means your project is:
A. Behind schedule
B. Ahead of schedule
C. On schedule
D. Cannot be determined
57) You are reporting that your project has a negative schedule variance. This means your project is:
A. Behind schedule
B. Ahead of schedule
C. On schedule
D. Cannot be determined
58) You are reporting that your project has a negative schedule variance and negative cost variance. This means your project is:
A. Behind schedule and over budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Ahead of schedule and under budget
59) You are reporting that your project has a negative schedule variance and positive cost variance. This means your project is:
A. Behind schedule and over budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Ahead of schedule and under budget
60) You are reporting that your project has a negative cost variance and positive schedule variance. This means your project is:
A. Behind schedule and over budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Ahead of schedule and under budget
No comments:
Post a Comment